Posts and Telecommunications Secretary Dr. Md. Mushfiqur Rahman today directed the officials concerned to quickly complete the work of the projects with sincerity and dedication.

He issued the directives at a review meeting of the annual development programme (ADP) of the posts and telecommunications division (PTD) held at its meeting room, said a press release.

The secretary mentioned that the division so far witnessed 20 percent physical progress of all the projects for the fiscal year 2024-25 (FY25).

The meeting also reviewed the implementation progress of the decisions of the previous meeting and implementation progress of the projects.

According to the IMED, the national progress of ADP implementation in the FY25 till August 2024 is 2.57 percent while the PTD recorded 11.67 percent till September 2024.

Mushfiqur Rahman said although the PTD’s ADP implementation rate in the FY25 is more than the national progress, there is nothing to be satisfied on it.

Mentioning that implementation of some ongoing projects have remained suspended due to shortage of allocation, he said work of those projects will have to be completed quickly as soon as the allocation will be available.

In the current financial year, PTD’s four departments have been implementing a total nine projects, of which BTCL has five, Teletalk one, directorate of posts two while Bangladesh Submarine Cable PLC has one project.

The project directors concerned presented the progress and implementation status in the meeting.

 